It is essential to monitor the cost and schedule of the project. One way to achieve this is by applying the Earn Value Management (EVM) technique.
The EVM technique helps forecast costs and schedule variance so preemptive actions can be taken to correct deviations. But before applying this technique, there is a lot to learn, like:
- Basics of EVM
- Various formulas for evaluating project performance
- Tracking cost and schedule
End your search for efficient project management today by learning about EVM and how it can be implemented across the different phases of a project.
Prerequisites
- Be open to learning
- Basic Excel Knowledge
- Quantitative Aptitude
- Project monthly consumption report
Key Terms And Definitions
Key Terms
Definition
Example
BAC
Budget at completion
Calculated budget to complete a project
PV or BCWS
Planned value or budgeted cost of work scheduled
The cost incurred as per the scheduled time
Planned Budget
AC or ACWP
Actual cost or actual cost of work performed
The actual cost incurred as per the current status of the project
EV or BCWP
Earned value or budgeted cost of work performed
The value of completed work as per the current status of the project
CV
Cost variance
Measure the cost performance of the project
If the CV is 0, the project is on budget
If the CV is +ve, the project is under budget
If the CV is -ve, the project is over budget
SV
Schedule variance
Measure the time performance of the project
If SV is 0, the project is on schedule
If SV is >1, the project is ahead of schedule
If SV is <1, the project is behind the schedule
CPI
Cost performance index
Measure the value of work done as per the actual cost spent
If CPI is 0, the project is on budget
If CPI is >1, the project is under budget
If CPI is <1, the project is over budget
SPI
Schedule performance index
Measure the performance of the project as per the planned schedule
If SPI is 0, the project is on schedule
If SPI is >1, the project is ahead of schedule
If SPI is <1, the project is behind the schedule
EAC
Estimate at completion
The estimated total cost to complete the project depends on the current cost situation and the progress of the work
ETC
Estimate to complete
The cost required to complete the remaining work of the project
TCPI
To complete the Performance index
It is the future CPI required to complete the project as per the BAC or EAC
Formulae
Terms
Formulae
Examples
PV or BCWS
% of planned work * BAC
EV or BCWP
% of work completed * BAC
CV
EV-AC
SV
EV-AC
CPI
EV/AC
SPI
EV/PV
EAC
BAC/CPI
If the project needs to be completed maintaining the current cost incurred
EAC
AC+( BAC- EV)
If the budgeted cost exceeds the current stage and the remaining work needs to be completed on time
EAC
AC+ [(BAC-EV) / (CPI * SPI)]
If the budgeted cost and time exceed the current stage and the remaining work needs to be completed on time
EAC
AC + bottom-up estimate to complete
If the cost of the remaining work is newly estimated
ETC
Bottom-up cost estimation
If the cost of the remaining work is newly estimated
ETC
EAC - AC
Depending on EAC calculation
TCPI
(BAC-EV) / ( BAC-AC)
If the project is currently under budget
TCPI
(BAC-EV) / ( EAC-AC)
If the project is currently over budget
Project Scenarios
Several scenarios will come up throughout a project. A deeper dive into these scenarios is necessary for effective project management.
Ideal Scenario
Details Available
Budget
$1,00,000.00
Completion Time
12 Months
Time Completed
3 Months
% Work Completed
25%
Cost Incurred Till Now
$25,000.00
Over Budget And Behind Schedule
Details Available
Budget
$1,00,000.00
Completion Time
12 Months
Time Completed
6 Months
% Work Completed
30%
Cost Incurred Till Now
$60,000.00
Over Budget And On Schedule
Details Available
Budget
$1,00,000.00
Completion Time
12 Months
Time Completed
6 Months
% Work Completed
50%
Cost Incurred Till Now
$60,000.00
Calculation Of Cost Incurred
The steps required for calculating the total cost incurred are:
- Find the value of the percentage profit margin of the last year
- Once the % profit margin of last year is known, then reduce the % profit margin from the hourly cost of the project
For example, if the hourly project cost is $50, then the actual figure will be
$50 - 10 % profit margin = $45 per hour
Actions for Efficient Implementation
Some action steps that can be taken to utilize the EVM technique learned today are:
- Define the cadence of EVM calculation monthly or every sprint
- Publish the EVM report on the cadence to your stakeholders
- Share the report in project review, account manager (1-1), service area lead, common channel, and with other stakeholders
- If there is a deviation, then raise the risk, add actions, and suggestions
- Monitor the Trend from the start of the project, the Previous month, or sprint
Corrective Actions
If there is a deviation in schedule and cost, then there is an expectation from a Project Manager and Account Manager to mitigate the risk collaboratively. In both scenarios, some action steps can be taken to deal with the variance. These action steps are listed below.
Scheduling Variance
- Raise risk ticket
- Discuss the risk with relevant stakeholders
- Share the risk with the client for visibility
- Identify staffing or technical debt
- Review the scope
- Analyze the committed vs. delivered work
Cost Variance
- Raise risk ticket
- Analyze the root cause
- Identify the opportunity for automation, like introducing a bot for DSM
- Identify staffing or technical debt
- Review the scope
Key Takeaway
After understanding the concept of EVM, budget control, and monitoring, users can start taking precautions. This can be done by following cost and schedule variance measures. It will help users mitigate the risk on time.
Bring this dispatch into a working session - one page in, scoping memo out.
Brief Foyer
